- Group Report
- Group: Mizuki, Alfredo, Chetan, Eric, Gianlucca
- Project Appraisal (Lecture 1)
- Project life cycle (Lecture 2)
- Stakeholder analysis (Lecture 2)
- The plan itself is not important, its the process of planning!
- Define Project Scope
- List Activities WBS
- Estimate Durations, Cost Time Resource
- Establish Relationships sequence
- Network Analysis- Time driven (resource usage and costs secondary)
- modeling process (fine tune the model)
- vary inputs, resources etc.
- check key criteria (At Risk (TM) software)
- Precedence Networks using Logic Link Line between Nodes
- Node properties:
- ES/EF (early start, finish), calculated during forward pass
- LS/LF (late start, late finish), calculated during backward pass
- TF = ES-LS (total float), when 0 it is a critical activity
- line linking all the critical activities is the critical path
- dur (duration), qty (quantity) -> together determine work rate
- desc (description)
- ID (task ID)
- ACTIVITY
- scope
- cost
- time
- resource
- Network Constraints:
- Finish to Start- default condition, act 2 can't commence until act 1 ends
- Start to Start- two tasks begin together
- Finish to Finish- example -> debris removal until drilling (ie rock, earth) finishes
- Start to Finish- not encountered in practice
- Example (units of duration are Days)
- Act. ID, Description, Duration, Successors
- START
- A,FORM,2,B C
- B,PLACE REBAR,4,D
- C,PLACE CONDUITS/SLEEVES,3,D E
- D, POUR CONCRETE,5,F
- E,CLEARING SURROUNDING,2,F
- F,SET CONCRETE,6
- END
- Forward pass
- ordinal method- goes from the same point in every day (end of day 1 to end of day 3 for a two day activity)
- date arithmetic- refers to the actual day (finish date - start date - 1) used by MS Project
- EF+duration = EF
- Free Float-is the amount
- Leads and Lags (adding constant times to tasks)
- Once a month is sufficient for MS Project Updating - Once a week is too frequent!
- 4 Resources: Manpower, Money, Machines, Materials
- Resource Smoothing- Must be done by hand (human involvement necessary?)
- Effects of Risk on Time, Scope, Cost and Quality
- identify probability of a risk, put them on an impact vs. probability
- identify effect of risk
- prioritize in terms of exposure, decide on mitigation
- Business Risks- market responses, inflation, weather, technology performance, performance of resources (project or corporate), currency movement
- insurable risks (pure risks)
- property damage (third party liability)
- loss of income
- Differentiate between project risk and technical risk
- project risks affect scope, time or quality
- Stages and documentation
- planning- risk management plan
- identification- risk register (database of risks)
- qualitative- impact prob. records, exposure & priority
- quantitative- exposure catalog
- responses mitigation
- monitor & control
- post project review and corporate risk register
Course work and notes from E. B. Holmes at the University of Edinburgh Business School (MBA, 2011-2012)
Thursday, February 2, 2012
Project Management (Lecture 3)
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment